| Activity | Urban area | Rural area | |
|---|---|---|---|
| New connection/additional load where supply can be provided from existing network | 30 days | 30 days | |
| Extension work or enhancement of transformer capacity is required | LT | 60 days | 90 days |
| HT | 120 days | 120 days | |
| EHT | 180 days | 180 days | |
Applications will be processed within 15 working days